With its experience in Africa and its agility in executing projects rapidly, Trafo Power Solutions is supplying three mini-substations and two transformers to a copper-zinc mine in the Democratic Republic of Congo.
David Claassen, Managing Director of Trafo Power Solutions, says the pressure was on from early in the planning stages to ensure this critical equipment would be available on time – to facilitate the continued mine expansion. From the date of the contract award, the company will deliver the units to the mine site within just four months – despite most of South African industry taking an annual December break.
“We have conducted projects previously with the end-client and the engineering, procurement and construction (EPC) contractor, so have a good understanding of their requirements,” explains Claassen. “This experience – combined with our history in the DRC and in the mining sector – gave us the edge in expediting the whole process.”
The order was for two 2000 kVA transformers to step down the electricity supply from 6,6 kV to 550V, as well as three dry-type miniature substations. Two of the mini-substations are rated 315 kVA and 6,6 kV to 400 V, while the third is a 630 kVA unit which also steps down from 6,6 kV to 400 V